Power Factor Correction (kVAr) Calculator

Calculate how many kVAr of capacitors you need to raise your power factor to the target, and how much the line current will drop.

Enter your installation data

Method

How is it calculated?

Qc = P × (tan φ₁ − tan φ₂)

P: active power (kW), φ₁: present, φ₂: target power factor angle. Example: 200 kW, power factor 0.78 → 0.95 gives Qc = 200 × (0.802 − 0.329) ≈ 95 kVAr.

Running on a generator: if capacitor banks stay connected while the site runs on a generator, the power factor can turn leading at low load and upset the generator's voltage control. The correction panel should switch out or limit its steps on transfer to generator. Sites with many drives or UPS systems need detuned (reactor) power factor correction.

Frequently asked questions

Why correct the power factor?

Generating reactive power locally reduces line current, losses and transformer/cable loading, and keeps you within your supplier's reactive energy rules.

What target power factor should I use?

Follow your electricity supplier's reactive energy limits; 0.95–0.99 is typical. Over-correction (leading) is also undesirable.

How should correction work on a generator site?

Capacitor steps should be switched out or controlled on transfer to the generator. JUTEK designs its power factor correction and ATS panels for this.

How many steps are needed?

The total kVAr is split into steps according to how the load varies during the day. More, smaller steps give finer correction for variable loads.